Refer to Figure 16.22 for the bill of materials and Table 16.8 for component inventory record information. Develop the material requirements plan for all components and intermediate items associated with product A for the next 10 weeks. The MPS for product A calls for 50 units to be started in weeks 2 6 8 and 9. (Warning: Safety stock requirements apply to items B and C.)
30
10
0
0
0
030
20
60
400
0
0Table 16.8
Inventory Record Data
Data Category
B
C
D
E
F
G
Lot-sizing rule
Lead time
Safety stock
Scheduled receipts
Beginning Inventory
L4L
2 weeks
150 (week 2)
3 weeks
50 (week 2)
POQ (P = 2)
None
6 weeks
400 (week 6)
1 week
40 (week 3)
FOQ = 100